SG4 Scaffolding: What SG4:22 Asks of a Scaffolder on Site
SG4:22 is the National Access and Scaffolding Confederation's (NASC) guidance on preventing falls while scaffolding is erected, altered or dismantled. Its full title is Preventing Falls in Scaffolding Operations, and it covers tube and fitting and system scaffolding. It's guidance and the law is the Work at Height Regulations 2005, though HSE names SG4 as a way of doing the job safely.
We read the full PDF for this guide. What follows is our summary, so check the document itself before you rely on a detail.
Who owns it and where to read it
NASC owns and publishes SG4. The current edition is dated November 2022, and Revision A of 14 September 2023 added an HSE foreword. Earlier revisions came in 2000, 2005, 2010 and 2015.
NASC's resource page opens the PDF, and its shop listed it at £0.00 on 31 October 2026. NASC aims the full document mainly at people who manage scaffolding operations. Scaffolders get a separate printed user guide, listed the same day at £9.85, or £4.90 for members. We didn't read the user guide, or the separate rescue plan guide, SG19, which costs non-members £16.35.
CISRS says full SG4 training is provided in the Part 1 course. Build UK's foreword in SG4:22 says all scaffolding operatives should hold a current CISRS card and be trained to it.
The scaffolders' safe zone
NASC says SG4:22 continues to emphasise the safe zone. It's collective protection built from platforms and guardrails, and the minimum is:
- a correctly boarded and supported platform, with no gaps someone could fall through
- a single main guardrail at least 950mm above the platform, wherever there's a risk of a fall
A finished platform for other trades needs more: double guardrails and toeboards, with no gap over 470mm. Inside gaps over 225mm, and openings such as windows, need guarding the same way where you could fall, with your harness as the last resort.
When you clip on
SG4 still expects harnesses, because the safe zone doesn't remove every risk of a fall. NASC strongly recommends that harnesses are issued to all scaffolders and worn at all times when working at height. See our scaffolding PPE checklist for the rest of the kit.
SG4:22 lists these as times to remain clipped on:
- before going within 1 metre of a leading edge
- before raising or lowering boards or decking
- before reaching below a scaffolders' guardrail
- when climbing or traversing the structure, such as crabbing a beam
- before accessing a boarded lift with no guardrails
- when traversing an unprotected platform, going no more than one bay before installing the guardrail
- while temporarily removing or adapting guardrails, until they're back and secured
On anchors, SG4 accepts ledgers, transoms and guardrails on load-bearing couplers, and plan braces on right-angle couplers. A standard only counts with an anchor device designed for it and no joint between the lift and the attachment point. It rejects ledgers or guardrails on putlog clips, puncheons, transoms at foot level or below, reveal ties and vertical braces. Anchor as high as you can on as short a lanyard as you can. If you're unsure of an anchor, SG4 says stop work and refer to your employer.
A single lanyard leaves you unprotected when you unclip to pass an obstruction, which is why SG4 calls for double lanyards on jobs like beam work.
Check your harness and lanyard at the start of each shift. NASC recommends a formally recorded detailed inspection at least every three months, and HSE suggests the same for frequently used kit in arduous work, scaffolding included. SG4 says any lanyard or harness that has arrested a fall should be destroyed.
Advanced guardrails and the other methods
SG4 describes several ways of getting a guardrail up before you step onto a lift:
- Scaffolders' step. It fixes to the main guardrail about 1m above the platform, so you can erect the guardrails above or remove them from below. You clip on before climbing on.
- Proprietary advanced guardrail systems. These keep edge protection in place while the permanent guardrails go on or come off. SG4 says they suit straight, uniform scaffolds, and tells employers to check whether the equipment can serve as an anchor point.
- Short lift. A temporary 1m lift between main lifts, so the ledgers and transoms above act as guardrails. It works on conventional lift heights of up to 2.1m, and you clip on climbing on and off.
- Tube and fitting advanced guardrails. Frame and horizontal versions built from standard components.
HSE's position is that "you don't have to use an advanced guardrail", though you do have to prevent a person falling during erection, alteration and dismantling.
NASC returned to this in 2026. On 20 July it told members that a letter had been sent to some of them making legal claims about current erection methods. NASC's notice said the regulations don't prescribe one erection method or mandate any product, and that SG4 offers a range of methods to choose from after a risk assessment. It doesn't say who sent the letter.
Rescue plans
Rescue planning is law. Regulation 4 says planning work at height "includes planning for emergencies and rescue". Schedule 5 says a personal fall protection system may only be used if the user and enough available people have training that includes rescue procedures.
SG4:22 says a rescue plan must be part of any system of work using personal fall protection, and must not rely solely on the emergency services. HSE says the same of the fire brigade, because the delay may be critical. The options SG4 sets out include:
- a scaffolder recovering themselves, or colleagues helping, without specialist kit
- site equipment such as a MEWP or a crane with a personnel basket
- retrievable inertia reels, which let colleagues winch someone to safety
- remote rescue kits used by trained people
- a rescuer descending to the casualty, as a last resort
NASC's guide to appointing a contractor says rescue plans must be in place before work starts on site whenever harnesses are used.
Where SG4 stands against the regulations
The Work at Height Regulations 2005 are the law. Regulation 7 requires employers to "give collective protection measures priority over personal protection measures", which is the same order SG4 follows. Regulation 14 requires you to use equipment provided as you were trained and instructed.
SG4 calls itself recommendations and guidance, and says it "should not be quoted as if it were a specification". HSE says safe erection "can be achieved by following" SG4 or similar guidance from system scaffold manufacturers. NASC says neither the regulations nor HSE treat any single method as the only route to compliance.
HSE's foreword warns of enforcement action against employers and scaffolding operatives who fail in their legal duties. SG4 reports a scaffolder given a six-month suspended sentence after working at about 20m with his harness unattached. NASC's guide for appointing contractors, which it suggests clients build into procurement, says scaffolding shall be erected in strict accordance with SG4.
Nothing we read from NASC or HSE says how a court weighs SG4, so we won't guess.
What the accident figures show
SG4:22 reports falls among NASC members dropping from 93 in 1999 to 12 in 2021. NASC's 2026 Safety Report counts 17 falls by operatives in 2025 and no operative deaths among contractor members. Of those falls, 14 were under 4m and three at 4m or above, the highest 22m. These figures cover NASC members only.
SG4 gives fragile roofs their own section. HSE reported in June 2026 that two companies were fined £79,300 in total after a scaffolder installing temporary edge protection fell more than 6m through a skylight. SG4 says to treat all roofs as fragile until a competent person has confirmed they aren't.
If you're a labourer
Two documents read differently here. SG4:22's harness recommendation excludes labourers, who it says are only permitted to access completed scaffolds. CISRS's labourer card page says an employer who deems you competent can issue a harness so you can work off a fully boarded platform with a single guardrail, and must provide and record SG4 harness training, because the COTS course doesn't include it. Ask your employer which applies before you go up. CISRS adds that labourers aren't permitted to erect, alter or dismantle scaffolding.
What employers on our board ask for
On 31 October 2026 ScaffJobs had 105 live listings, and employers' own pages named SG4 for 12 roles at four firms. Altrad's seven scaffolder adverts tell you to adhere to SG4 requirements. Ashton Scaffolding wants thorough knowledge of TG20 and SG4 from a chargehand. Coventry Scaffolding names it for a contracts manager, a contracts supervisor and an estimator, and East Coast Scaffolding for advanced scaffolders. One more listing that applies by email names it too.
None of the 51 employer pages we read mentioned the safe zone, advanced guardrails or a rescue plan by name.
Browse live scaffolder jobs, labourer roles, or read our guide to the Work at Height Regulations.
Common questions
- What is SG4 in scaffolding?
- SG4:22, Preventing Falls in Scaffolding Operations, is guidance from the National Access and Scaffolding Confederation (NASC). It covers tube and fitting and system scaffolding, and sets out how to prevent falls during erection, alteration and dismantling.
- Is SG4 a legal requirement?
- SG4 is guidance, and NASC says it shouldn't be quoted as a specification. The law is the Work at Height Regulations 2005, and HSE says safe erection can be achieved by following SG4 or similar guidance from system scaffold manufacturers.
- When do you have to clip on under SG4?
- SG4:22 says to clip on before going within 1 metre of an unprotected edge, before raising or lowering boards, before reaching below a scaffolders' guardrail, and when climbing or traversing without a safe zone. You stay clipped on while guardrails are temporarily removed.
- Do you have to use advanced guardrails?
- No. HSE says you don't have to use an advanced guardrail, but you do have to prevent a person falling during erection, alteration and dismantling. SG4 sets out the different methods available.
- Is SG4:22 free?
- Yes. On 31 October 2026 NASC's shop listed the SG4:22 PDF at £0.00. The printed user guide for scaffolders was £9.85, or £4.90 for members.
Related guides
CISRS Cards Explained: Levels, Costs and How to Get One
What the CISRS card is, the levels from labourer to advanced scaffolder, what each roughly costs, and the route to getting qualified on UK sites.
How to Become a Scaffolder in the UK With No Experience
How to get into scaffolding with no experience: the labourer route, apprenticeships, the card and test you need, and what the job is really like.
How Much Do Scaffolders Earn in the UK? £25,000 to £51,000
UK scaffolders earn around £25,000 a year starting out and about £51,000 once experienced (National Careers Service). How day rates, cards and region move pay.